Clogau Level 5: Blast Update
Last Friday at Clogau, the team completed another controlled drill-and-blast cycle at Level 5. The round delivered an advance of approximately 1.1 metres, with ground conditions appearing to improve following the blast, which is a positive for the next round of drilling and blasting.
Work continues with the usual disciplined sequence of ventilation and checks, inspection, and preparation for the next cycle, as the Level 5 development progresses. Total advance to date is approximately 10.9 metres.
#Clogau #Wales #UndergroundMining #OperationalUpdate #BulkSampling #Exploration #Mining #MiningSafety #ResponsibleMining #ESG #AlbaMineralResources